Employer: Soma Cement Industry and Trade Inc.
Contractor: Kuark Industry A.Ş.
Name of Work: Various Volumes of Water Tanks
Content of the Work Done: Manufacturing and delivery of 4 vertical drums made of 10 mm thick S235JR material with a storage capacity of 10 m3. Manufacturing and delivery of 1 vertical drum made of 6 mm thick S235JR material with a storage capacity of 4 m3.


1/1
Employer: Soma Cement Industry and Trade Inc.
Contractor: Kuark Industry A.Ş.
Name of Work: CO₂ Inertization System Copper Pipelines
Content of the Work Performed: Manufacturing and assembling of 18 & 28 copper pipes for carbon dioxide inertization for Coal mill, bag filter & coal powder bin equipment in Soma Cement factory.